Site Conditions for Shoring Work and Materials Needed for Secant Shoring


 

When a building is built on sandy soil or soft ground, at such times, it becomes necessary to construct a secant pile wall. Secant pile wall, ensure that the structure behind the wall would remain proper and it won't have the risk of falling due to high lateral pressure working. 

 

This work is carried under the expert supervision of a quality engineer, construction manager, safety officers, and skilled labor. For this work, rotary drilling rigs ensure that the soil remains firm and the surrounding structures are not disturbed. 

 

This article will explain the site conditions for performing the shoring work and the material needed to construct sheet piles in Dubai. 

 

Site condition for shoring work

The subsurface of the area is made up of loose sand accumulating on the top layer. The medium and the layer below are made up of the formation of calcarenite and sandstone over time.

 

The reason to construct secant piles is to ensure they do to the depth into the calcarenite and sandstone. This will, in turn, help maintain the linkage between the concrete and the ground. 

When it comes to the elevation of water, it all depends on the tidal and seasonal changes. 

 

Materials needed for construction of secant shoring

Following are the materials needed for the proper construction of secant shoring.

 

1- Materials needed for constructing secant pile wall

The primary and the secondary piles are made up of concrete. The primary piles have an FEU (forty-foot equivalent unit) of 20N/mm2. The secondary pile has an FEU of 40 N/mm2. 

The high yield strength of the bars should be 460 N/mm2. You also need to have spacers. 

 

2- Anchor materials 

For grouting, HDPE pipes are used. The cement used for grouting is CEMI 32,5 or CEMI 42,5. The ratio of cement and water of grout is to be in the range of 0.4 to 0.55. This helps the mixture attain comprehensive strength of 25-30 N/mm2. 

 

Only one tendon anchor strand is used. The tendons formed are made with a 6-wire strand using class 2 relaxation. 

 

For example, if you use 100kgs of cement grout mix, you need to use 55 liters of water. 

 

In conclusion

This was an insight into secant shoring. Get in touch with reliable suppliers of secant shoring to get maximum ROI on your project. Companies like Universal Piling Company are good choices. They have proven their mettle on prestigious projects like the Etihad Rail that connects the seven emirates of UAE.